The Vincennes Mayor’s Office says all the asphalt is down, except for the surface layer, on the Washington Avenue project.
City officials say the last layer will wait until the very end of the project.
They also say several more driveways were poured last week as well and sub-contractors got started pouring light pole foundations.
Also, wall materials arrived for a retaining wall that will be constructed between Old Orchard and Niblack Boulevard.
This week crews will continue with concrete flat-work, more light pole foundations, and will likely start on the foundation for the retaining wall.
-Washington Ave. Project Update